Balancing Cost and Urgency for a Critical Infrastructure Project

Different components had different delivery priorities. A split-mode freight strategy helped keep the project schedule on track without moving the entire shipment by air.

Business Challenge

Network cabling equipment was required for a critical hospital infrastructure project in Raipur.

Different components had different levels of urgency. Moving the entire shipment by air would increase freight cost, while relying entirely on ocean freight could affect the project schedule.

The customer needed a logistics strategy that balanced delivery priority with freight cost without compromising the required deployment timeline.

Solution Designed

A split-mode freight strategy was designed around the urgency of each part of the shipment.

65% of the cargo moved by air freight to support critical project phases, while 35% moved by ocean freight for greater cost efficiency.

The ocean movement was routed through Nhava Sheva and Delhi, while customs clearance and final delivery were managed across both freight flows to keep the shipments aligned with the project requirement.

Business Impact

Project Timeline Maintained with a Balanced Freight Strategy

All shipments reached the project site within the required timeline.

The combination of air and ocean freight supported critical deployment phases while providing a more cost-conscious option for cargo that did not require urgent uplift.

The customer was able to maintain the planned infrastructure deployment schedule without treating every shipment as time-critical.

Customer Experience

Priority-Based Freight Planning

Each shipment was matched to the transport mode based on its delivery urgency.

Air & Ocean Freight Execution

A 65% air and 35% ocean split balanced project timelines with freight cost.

Customs & Final Delivery

Clearance and onward transportation were managed across both freight flows.

Project-Focused Logistics

Multiple shipments and transport modes were managed against one required project timeline.

Planning Cargo with Different Delivery Priorities?

A combination of air and ocean freight can help balance shipment urgency, project timelines and freight cost.